Week 3 & 4 Term Three


Week 4
As soon as the structural steel was secured in place, the timber framing was put up.  The team are now preparing the first floor with the installation of concrete beams to support the concrete floor.




Week 3
Early this week we had a crane on site and parked up on Hackthorne Rd lifting into place all of the structural steel for the ground floor.