The steel posts for the retaining wall have been delivered and are being put into place.
logo
Monday, 20 June 2016
Friday, 3 June 2016
Week 5 Update
An update from our project manager ...
Saturday the 4th of June
"HRS Construction has completed the earthworks on time despite the recent rainy weather. Holes up to 3m deep will be drilled along the two rear sides of the new two storey learning hub so 23 heavy duty steel posts can be cast into the ground to support the bank. The new retaining wall will be 3.5m high at the highest point in the corner of the site. HRS Construction now has a fully operational site office, toilet, first aid room and tool store container on site. HRS has also removed part of the fencing mesh/cloth so the children can follow progress from the play area."
David Kolien, Project Manager

Thursday, 26 May 2016
HRS Site Office and Tool Sheds arrive
This week we again saw a rather large crane park up on Hackthorne Rd. This time, the HRS site office and tool container/shed was delivered to their site.
Wednesday, 18 May 2016
Week 3 Term Two
Just a couple more photos of the site being excavated. For more information check out this update from our project manager
Sunday, 15 May 2016
Tuesday, 10 May 2016
Friday, 6 May 2016
Demolition Week
Over the first week of term the remaining classrooms (room 5) were demolished. The site is also starting to be cleared of all foundations etc.