Monday, 20 June 2016

Week 8 : The Retaining Wall

The steel posts for the retaining wall have been delivered and are being put into place.



Friday, 3 June 2016

Week 5 Update


An update from our project manager ...

Saturday the 4th of June

"HRS Construction has completed the earthworks on time despite the recent rainy weather.  Holes up to 3m deep will be drilled along the two rear sides of the new two storey learning hub so 23 heavy duty steel posts can be cast into the ground to support the bank.  The new retaining wall will be 3.5m high at the highest point in the corner of the site.  HRS Construction now has a fully operational site office, toilet, first aid room and tool store container on site.  HRS has also removed part of the fencing mesh/cloth so the children can follow progress from the play area."

David Kolien, Project Manager





Thursday, 26 May 2016

HRS Site Office and Tool Sheds arrive

This week we again saw a rather large crane park up on Hackthorne Rd.  This time, the HRS site office and tool container/shed was delivered to their site.


Wednesday, 18 May 2016

Week 3 Term Two

Just a couple more photos of the site being excavated. For more information check out this update from our project manager




Sunday, 15 May 2016

Site excavation continues...

Week 3 of the term and progress continues on the build site. The site is now being excavated.


Tuesday, 10 May 2016

Friday, 6 May 2016

Demolition Week

Over the first week of term the remaining classrooms (room 5) were demolished.  The site is also starting to be cleared of all foundations etc.